Owners Representative consultant on The LaGuardia Airport(LGA) Central Terminal Building Redevelopment. Led the Concessions Tenant build out program and supported LGP’s direct work program.
Conducted integrated review of Base Building and Tenant designs for coordination, deliverables and conflicts
Established Work Plan process to address logistics, facilitate overlapping Base Building/Tenant construction to maintain positive program schedule progress.
Created Tenant construction guide included design compliance, site access, compliance, safety and security information with input from Skanska, LGP, Port Authority
Stakeholder Support and Management
- LaGuardia Gateways Partners program status, developments, issues and resolutions
- Skanska established collaboration practice with Directors, Superintendents, Designers managing schedules, conflicts and safety protocols
- Port Authority managed Tenant design submissions, Rider issues, permitting, delays, inspections and closeout
- Tenant/contractor schedule, progress, issue reviews, Logistics Work plan planning, and Master schedule compliance
- Project Controls Tenant/LGP Master Schedule update, coordinate Change scope details and costs with Change manager
- Adhoc sessions with LGP, Port Authority, Skanska,Tenant Teams to address specific events or issues
- COVID crisis team member in development of site safety response to CDC guidance and management of Tenant engagement and notifications.
Reporting
- Executive Summary dashboard highlighted: A. Program status snapshot, B. Critical issues, C. Project Planning and Design, D. Tenant issues E. Port Authority Status
- Program Mobilization: Pre-construction report tracking Design stage, Port Authority Approval, Tenant Commercial agreement, Contractor mobilization, Schedule milestones and issues
- Tenant Program dashboard: Design and Permit approvals, Contractor agreement, Procurement, Progress, Testing, Inspections
- Tenant and Contractor oversite: Tenant project report tracked Action items, Issues and response
- Skanska White box scope delivery: maintained detail status, progress and delay impact